Responsibilities and obligations are ramped up in the new CDM regulations

The Construction (Design & Management) Regulations 2015 are due to come into force on 6 April this year, as Stacy Sinclair mentioned in her legal column in March. The industry will need to get to grips with significant changes, including: dropping of the CDM co-ordinator role; introduction of the role of principal designer; increased client duties; application of regulations to all construction projects whether or not they are notifiable; and application of the regulations to domestic clients.

The role of CDM co-ordinator will be replaced by principal designer. Whether or not the project is notifiable, clients will need to appoint a principal designer, who will have control over the pre-construction phase of the project. He will be responsible for planning, managing and monitoring that phase and for co-ordinating matters relating to health and safety during it. The principal designer will also be required to assemble pre-construction information at the outset of the project, prepare the health and safety file and (if still involved at this stage) hand this over to the client at its end. Principal designers will need ‘the understanding and skills to manage and co-ordinate the pre-construction phase, including any design work carried out after construction begins’.

Health and safety designed-in

Changes to the Regulations are intended to put responsibility for the management and co-ordination of health and safety issues at the heart of the design team. Consequently, architects and lead consultants are likely to be asked to take on this role, at least before works start on site.

Changes to the Regulations are intended to put responsibility for the management and co-ordination of health and safety issues at the heart of the design team

If they are to be appointed as the principal designer, architects will need to consider how they discharge this responsibility as they may not have the in-house expertise to carry it out. They will need the skills, knowledge, experience and organisational capacity to fulfil the role. To discharge its obligations as principal designer, the architect may consider appointing a health and safety advisor/CDM consultant as a sub-consultant to help it discharge its obligations as principal designer. On design and build projects, however, clients may flip the role to the main contractor once the main contract begins.

Transitional provisions will mean CDM co-ordinators appointed before 6 April 2015 can remain in place on existing projects until either the project comes to an end or 5 October 2015 is reached, whichever is earlier. After this the role will disappear. A hybrid set of obligations will apply to CDM co-ordinators retained during the transitional period.

CDM 2015 has also ramped up client obligations again. HSE guidance talks of clients taking ownership of these arrangements, and express reference in the 2007 Approved Code of Practice to the client being able to rely on advice from the CDM co-ordinator on making these arrangements has been removed. The client must also ensure the health and safety file is produced, rather than the CDM co-ordinator taking sole responsibility for it.

Know your obligations

Although CDM imposes obligations on domestic clients for the first time, these obligations will normally be discharged by designers, contractors and consultants appointed by the client. Architects will therefore need to understand those obligations they are required to carry them out for domestic clients. 

CDM 2015 is likely to result in architects being required to discharge greater obligations in respect of CDM than they are under the old regulations. Architects will therefore need to acquaint themselves with the requirements of CDM 2015 and ensure they have adequate resources to discharge them. •

Angus Dawson is partner at Macfarlanes


 

HEALTH AND SAFETY FILE

Under CDM 2015, the principal designer will be responsible for preparing or updating the health and safety file. During the pre-construction phase, the principal designer will be responsible for preparing a health and safety file which is ‘appropriate to the characteristics of the project’ and contain information likely to be needed during the subsequent project to ensure people’s health and safety. The principal designer will be required to regularly review and update the file. The principal contractor is obliged to provide the principal designer with any information which ought to be included in the health and safety file. If the principal designer’s appointment concludes before the end of the project, it must pass the health and safety file to the principal contractor, who will then become responsible for finalising the file and handing it over to the client at the end of the project.

 

Latest

A love of libraries and a mission for mass timber helped Madrid’s SUMA win the EUmies Award for Emerging Architecture for its Gabriel García Márquez Library in Barcelona

Interview with the Spanish architect of Gabriel García Márquez Library

Built-in cement plants and mycelium-inspired towers? SOM and Illinois Institute of Technology unite to produce Masters in tall buildings considering future cities in the context of density and climate change

Built-in cement plants and mycelium-inspired towers

Berlin architects Gustav Düsing and Max Hacke see their project for the Technical University at Braunschweig take the prize for viable, sustainable and cultural design

Sustainable project for the Technical University at Braunschweig takes coveted prize

The outward-facing, sustainable, timber Gabriel García Márquez Library in Barcelona gives Madrid-based SUMA Arquitectura the prize with its transformative community impact

Gabriel García Márquez Library rethinks the typology

Learn more about nurturing practice-client relationships and turning the short-term into the long-term

Learn more about nurturing practice-client relationships and turning the short-term into the long-term