img(height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=2939831959404383&ev=PageView&noscript=1")

Change management

Words:
Dr Stacy Sinclair

Changing contractors can be more expensive than you think

Supporters of the JCT suite of standard form contracts refer to the fact that many of its clauses are ‘tried and tested’ in the courts. This gives parties to the contract the security of knowing how the courts are likely to approach and interpret JCT provisions. Opposers say the fact that the Court has had to hear so many disputes over the years on the JCT contract is evidence that it does lead to disputes. Whichever side of the fence you sit, if you are a contract administrator it is worth understanding the court’s recent interpretation of clause 2.30 of the JCT Intermediate Form (2005).

Clause 2.30 provides either for defects to be rectified by the contractor in the ‘Rectification Period’ following practical completion or, if the employer consents and the administrator so instructs and such defects are not put right, an ‘appropriate deduction’ from the contract sum is to be made.

The question before the court in the recent case of Oksana Mul v Hutton Construction Ltd was, effectively, what is an ­‘appropriate deduction’ when the employer arranges for a different contractor to complete works/defects which are not in accordance with the contract?

What is an ‘appropriate deduction’ when the employer arranges for a different contractor to complete works/defects?

In this case, Hutton was engaged by Mul to carry out various substantial extension and refurbishment works to a large country house in Kent. The contract sum was approximately £3m and work started in May 2008. Practical completion was awarded in May 2010 and the final sum certified was approximately £4m. In March 2011 the contract administrator notified Hutton that it was arranging for all outstanding works/defects to be carried out by other contractors.

Mul argued that the deduction should be appropriate in all the circumstances and could be:  The contract rates/priced schedule of works/specification; the cost to the contractor of remedying the defect (including sums to be paid to third parties engaged by the contractor); the reasonable cost to the employer of engaging another contractor to remedy the defect; or the particular factual circumstances and/or expert evidence relating to each defect or remedial works.

Hutton argued that the appropriate deduction would invariably refer to the rates or prices in the priced document.

Agreed, but...

The judge agreed with Mul: any of those deductions could be appropriate. He pointed out the employer may want to arrange for the remedial works to be carried out by others – either simply for convenience or because the employer has (either justifiably or not) become fed up with the contractor and wants no more to do with him. Either way, clause 2.30 expressly allows the employer to do so and still recover reasonable costs.

However, the employer must be mindful of his obligation to mitigate the contractor’s loss. The judge held that if the employer acted unreasonably in not giving the contractor a fair opportunity to put right defects for which it was responsible, the employer would probably have failed to mitigate that loss. This is simply in line with previous case law.

Contract administrators therefore need to fairly and independently value the ­appropriate deduction under Clause 2.30 by reference to the rules of mitigation of damage. Under previous case law the employer is generally limited to what it would have cost the original contractor to remedy the defects had it had the opportunity.

As the costs of the original contractor returning to site are likely to be less than if the employer engages a new contractor, employers and contract administers must be alert to notifying the contractor of the defects and giving him the opportunity to return to site to rectify. If not, the employer may well have to fund the added costs of a new contractor. 

Stacy Sinclair is with Fenwick Elliot

 

PRACTICAL COMPLETION

This is not a defined term within JCT contracts. Previous case law defines practical completion (PC) as the completion of the works for all practical purposes, allowing the employer to take possession of the works and use them as intended; completion of the works where very minor de minimis work has not been carried out and there are no patent defects. PC triggers certain events such as the end of the contractor’s liability for liquidated damages.

In Mul v Hutton, PC was certified by the contract administrator with a certificate attaching to it a substantial list of works said to have been incomplete or defective. Apparently this was owing to the employer’s need or desire to move in. Nevertheless, contract administrators should be mindful of certifying PC when patent defects are known and there are still substantial outstanding works. In any event, as the judge pointed out, any post PC interim certificates must take into account known defects in the works.

 

External management
External management

Latest

The debut project by craft-led architect Grafted celebrates the original detailing of a house in Norwich’s Golden Triangle through concrete panels which the practice cast itself

Grafted’s debut project celebrates the original detailing of a house in Norwich’s Golden Triangle

Building-scale installation validates use of reclaimed timber for structural glulam and cross-laminated timber frame construction

Building-scale installation from waste points way to circular economy

Rescue and restore a William Adam-designed villa, create an outdoor installation ‘filled with play, wonder and delight’, imagine a multifunctional exclusive/inclusive complex that serves client and community - some of the latest architecture contracts and competitions from across the industry

Latest: Bid for phase 1 rescue of Scotland’s first Palladian country house

A journey to Turkey for a summer wedding prompts the Purcell architect to consider aspects of place and time

Joining the dots to make sense of disruption

Emulating the patterns of natural light and our deeply embedded responses to it are central to lighting design, said experts at the RIBAJ/Occhio lighting event

Light and atmosphere are the key to making a magical place